Customer: Eisenbahn-Hochleistungsstrecken AG
Construction period: 06.2000 – 12.2004
Location: Lower Austria
Country: Austria
“Wagram intersection”, St. Pölten freight train bypass
The project is divided into three contract sections, contract section 1 for the Pottenbrunn train station, contract section 2 for the actual intersection between the new section, freight train bypass and enlarged section and contract section 3 for the entrance road into the town of St. Pölten.
The primary purpose of the construction is to join the existing double-track West railway line with the new (NBS) Vienna – St. Pölten section and the planned (GZU) St. Pölten freight train bypass. The construction work will require a number of temporary measures such as a diversion of the S 33 and 2.5 km of the West railway line. The construction work also includes a diversion of the L 5083, L 5086 and L 2200 federal roads and a number of local roads.
Technical data
Total length of tracks: 30 500 m
Length of enlarged road section: 6175 m
Length (new contract section/freight train bypass): 3000 m
Tunnel single track: 345 m
Tunnel double track: 665 m