Customer: GDDKiA
Construction period: 10.2010 – 08.2013
Location: A1, Świerklany – Gorzycki
Country: Poland
Continuation of construction of motorway A1, section “Swierklany” – “Gorzyczki”, through ALPINE Bau. The project includes the southern section of the Polish motorway A1. When fully completed, it will be 582 kilometres long and run from Gdansk up to the border of the Czech Republic near Ostrava.
The contract section is 18.33 km long and runs from the future junction at the city of Świerklany to the border between Poland and Czech Republic near the village Gorzycki. The contract also includes the construction of two junctions near the cities of Mszana and Gorzyce, a motorway service area for each direction and a toll-gate.
The motorway will have 2 lanes on each side with a possibility to extend it to 3 lanes each. 32 bridges will be built along the roadway, one of which will be the centrepiece – a 380 m long cable-stayed bridge across the valley of the Kolejówka stream.
Client has already approved and accepted the project, except the cable-stayed bridge MA 532 which has to be completed. Traffic operation will be able to commence in 2013